Increase your chances of passing the FIDIC CCM exam questions on your first try. Practice with our free online CCM exam mock test designed to help you prepare effectively and confidently.
The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition 1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract backto-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions: "Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer's Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause 5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer's Requirements, its items of reference or Contractor's design of the Works for the scope part for which Subcontractor is contracted." What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?
Under the FIDIC Yellow Book (both editions), the Contract is administered by the Employer (unless it appoints an Employer's Representative) who endeavours to reach agreement with the Contractor on each claim. Is this statement true or false?
Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?
Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme? Choose all of the correct answers (multiple possibilities)