Free PMI-CP Mock Exam – Practice Online Confidently

Increase your chances of passing the PMI PMI-CP exam questions on your first try. Practice with our free online PMI-CP exam mock test designed to help you prepare effectively and confidently.

Exam Code: PMI-CP
Exam Questions: 177
Construction Professional in Built Environment Projects
Updated: 25 Aug, 2026
Question 1

An organization kicked off a large construction project of a three-year duration. Due to its importance to the national economy, the government obliged the organization to submit a monthly report including progress description, financial status, change orders, and forecasting measurements. After creating the first report, the organization found that it takes too much time to manually generate the report and therefore decided to leverage technology to meet the government requirements.What technologies could the organization use? (Select two)

Options :
Answer: A,B

Question 2

While controlling the project execution, the construction professional uncovers scope creep caused by a key stakeholder. When checking the Stakeholder Engagement Assessment Matrix, the construction professional finds out that the stakeholder is classified as “committed”.What should the construction professional do?

Options :
Answer: C

Question 3

A construction professional is asked to execute a power plant project using the Last Planner System® approach. What are the five connected conversations of LPS

Options :
Answer: A

Question 4

Upon the increasing number of accidents in a large construction project that employs hundreds of workers, the steering committee decides to track the locations of everyone on the field to ensure quick interventions.What technology should the construction professional use in order to implement the steering committee decision?

Options :
Answer: B

Question 5

A senior construction professional works on a nuclear power plant which will be planned and executed using the Advanced work packaging (AWP) approach. After the definition of construction work areas (CWAs), the construction professional moved on to the preparation for the workface planning phase. One of the project planning team wondered about the relationship between the Engineering Work Packages (EWP), the Construction Work Packages (CWP), and the Installation Work Packages (IWP).What should the construction professional’s answer be? (Select two)

Options :
Answer: A,D

Viewing Page : 1 - 18
Practicing : 1 - 5 of 177 Questions

© Copyrights FreeMockExams 2026. All Rights Reserved

We use cookies to ensure that we give you the best experience on our website (FreeMockExams). If you continue without changing your settings, we'll assume that you are happy to receive all cookies on the FreeMockExams.