Free PMI-RMP Mock Exam – Practice Online Confidently

Increase your chances of passing the PMI PMI-RMP exam questions on your first try. Practice with our free online PMI-RMP exam mock test designed to help you prepare effectively and confidently.

Exam Code: PMI-RMP
Exam Questions: 280
PMI Risk Management Professional
Updated: 24 Aug, 2026
Question 1

A Scrum team has recently lost its product owner to another team. A new product owner has been hired for the Scrum team. This product owner is currently new to the project, unfamiliar with the team's practices, and does not have a full grasp of the product users. After a few sprints, the product owner is receiving constructive feedback from both internal and external stakeholders related to the direction of the product and its current challenges. What can the product owner do to improve the product's perception among stakeholders and ensure the team understands the product vision? (Choose 2) 

Options :
Answer: A,C

Question 2

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize. What should the project manager do next?

Options :
Answer: A

Question 3

Upon reviewing the risk analysis results, the project manager notices several risks that occur more frequently than others. What should the project manager do? 

Options :
Answer: D

Question 4

A new project to develop a custom software solution for a high-profile client is being initiated. The project sponsor emphasizes the importance of delivering the solution on time and within budget, as this project could lead to significant future opportunities. The risk manager recognizes that the team lacks a standardized approach to managing risks and that some team members are unfamiliar with risk management practices. What should the risk manager do?

Options :
Answer: B

Question 5

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves. What should the risk manager do to mitigate the chance of the same issues reoccurring?

Options :
Answer: D

Viewing Page : 1 - 28
Practicing : 1 - 5 of 280 Questions

© Copyrights FreeMockExams 2026. All Rights Reserved

We use cookies to ensure that we give you the best experience on our website (FreeMockExams). If you continue without changing your settings, we'll assume that you are happy to receive all cookies on the FreeMockExams.