Free PMI-SP Mock Exam – Practice Online Confidently

Increase your chances of passing the PMI PMI-SP exam questions on your first try. Practice with our free online PMI-SP exam mock test designed to help you prepare effectively and confidently.

Exam Code: PMI-SP
Exam Questions: 325
PMI Scheduling Professional
Updated: 01 Apr, 2026
Question 1

Which of the following provides a method to track project progress during project execution against what was planned?

Options :
Answer: C

Question 2

You are the project manager for your organization. You are working with your virtual team to create activity duration estimates for your current project. This virtual team is comprised of team members from around the world. Much of this process will be completed by geographical locations though some conferences will require all the team members to participate and to coordinate the activities that will interact between the different sites. The project manager must consider all of the following when creating the activity duration estimates except for which one? 

Options :
Answer: B

Question 3

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule performance index? 

Options :
Answer: C

Question 4

In which of the following group decision making techniques does the largest block in a group decide the group decision even if a bulk is not achieved? 

Options :
Answer: D

Question 5

You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms. What type of an estimate are you creating in this scenario? 

Options :
Answer: A

Viewing Page : 1 - 33
Practicing : 1 - 5 of 325 Questions

© Copyrights FreeMockExams 2026. All Rights Reserved

We use cookies to ensure that we give you the best experience on our website (FreeMockExams). If you continue without changing your settings, we'll assume that you are happy to receive all cookies on the FreeMockExams.