Question 1

A supplier was supposed to mobilize a government-issued, licensed piece of equipment two days ago, but did not. The procurement manager was informed that the supplier failed to check the validity of the license, which expired last week. The supplier had already submitted an application to the authorities, but it generally takes one to three weeks to process the application, which will affect the critical path. Which action should the project manager take?

Options :
Answer: C

Question 2

A project team with members from many different countries is struggling to cooperate The project manager accepted these difficulties during the storming phase of team development, but the team has not moved to the next phase The project is beginning to fall behind schedule What can the project manager do to move the team to the norming phase?

Options :
Answer: A

Question 3

An agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team's performance is not good, and some team members want to leave the team. How should the project manager approach this situation?

Options :
Answer: C

Question 4

A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders. What should the project manager do?

Options :
Answer: D

Question 5

A project manager is developing a project baseline schedule and has started to assign team members to the project activities according to their function. What should the project manager do in this phase?

Options :
Answer: B

Viewing Page : 1 - 207
Practicing : 1 - 5 of 2069 Questions

© Copyrights FreeMockExams 2026. All Rights Reserved

We use cookies to ensure that we give you the best experience on our website (FreeMockExams). If you continue without changing your settings, we'll assume that you are happy to receive all cookies on the FreeMockExams.