ABC Company has a standard course development model with four defined stages that the company manages using PRINCE2. The project manager for the Health and Safety Training Project has recommended the stage 2 of the standard model be split into two separate stages. As a result, there will now be five management stages in the project. Is this an appropriate application of the ‘tailor to suit the project’ principle, and why?
During the 'create the project plan' activity as part of the initiation stage, the project manager identifies several threats to the project timescales. These threats relate to stage 3 products. Therefore, the project manager decides to wait until the end of stage 2 to assess the risks to the project plan. Is this an appropriate application of the plans theme, and why?
The 'e-learning course' is being delivered by an external consultancy. The testing of the e-learning has been completed by ABC Company’s testers and some faults have been found that still need to be fixed. The team manager for the 'e-learning course' work package believes the faults can be fixed within existing work package tolerances and has raised a request for change with the project manager. Is this an appropriate action, and why?
Which 2 statements should be recorded under the Business options heading?
During which process would the stage tolerances be set?