Question 1

The delivery of the pilot courses has been split into two separate products: ‘planned pilot courses’ and ‘delivered pilot courses’. ‘Planned pilot courses’ will be produced during stage 3, and the ‘delivered pilot courses’ will take place during stage 4. This will allow the project board to approve the plan for the pilot courses before the resources are committed to delivering the pilot courses. Why is this an appropriate application of the plans theme to control the project? 

Options :
Answer: D

Question 2

The Sales Director would like to add a new company logo to the 'marketing material'. The change to the project scope has been approved by the project board. It is expected to delay product and stage completion date by 3 days and cost £900. The stage 2 cost tolerance of +£1,000 has not been used. The change budget of £500 has not been used. Which option describes how this change should be funded?

Options :
Answer: D

Question 3

Which of the following statements is NOT correct? The Learn from Experience principle suggests that lessons should be actively sought...

Options :
Answer: B

Question 4

A construction company that is one of ABC Company’s key clients has agreed to provide a member of the staff to review and comment on the ‘e-learning course’. Which stakeholder interest should the member of staff represent, and why?

Options :
Answer: C

Question 5

While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of £250k, but was undecided on the Change Authority to recommend. Which option is an appropriate Change Authority for the Outsourcing project?

Options :
Answer: B

Viewing Page : 1 - 38
Practicing : 1 - 5 of 375 Questions