Question 1

Peter is a new Product Owner on a newly formed Scrum Team. Peter has projected a product completion date
based on an estimated velocity of 21 completed points per Sprint. After the first 3 Sprints, the team has
determined that their maximum velocity is 15 points and they are unable to create shippable increments at the
end of each Sprint.
What is the best way to proceed?

Options :
Answer: D

Question 2

How much work must a Development Team do to a Product Backlog item it selects for a Sprint? 

Options :
Answer: B

Question 3

A Scrum Team selected a Product Backlog item during Sprint Planning. However, at the end of the Sprint the work does not meet the Definition of Done. What two things should happen with this incomplete Product Backlog item? (Choose two.)

Options :
Answer: B,D

Question 4

Steven, the Scrum Master, observes that one of the Development Team members is not attending the Daily
Scrum. The Development Team feels this is ok as they all sit in the same area and already have constant
communication throughout the day.
Which is the best action for Steven to take?

Options :
Answer: C

Question 5

At the eighth Sprint Review, the stakeholders are upset that the product being built is not what they expected
and will incur additional costs that was not planned for.
What may have led to this?

Options :
Answer: B