Question 1

The architect's contract with the owner has a budget of construction cost, and the architect has established a budget of cost in the mechanical engineer's contract. The mechanical bid package is 36% over the budget. What is the engineer required to do?

Options :
Answer: B

Question 2

The architect is on site to evaluate the completed work by the contractor. During the evaluation, the architect notices a structural connection that deviates from the contract documents. According to AIA B101, to which party should the architect report this observed deviation?

Options :
Answer: D

Question 3

According to ATA Document C401, Architect-Consultant Agreement, clearances and tolerances required by the mechanical work relative to the structural system are coordinated through which one of the following parties?

Options :
Answer: C

Question 4

What is the primary purpose of a construction schedule? 

Options :
Answer: B

Question 5

An architect is evaluating a change order. Where should the costs for the project superintendent or general foreman be included?

Options :
Answer: C